灯光材料如下

1

2

3

将积木拆开如下

Lighting materials are as follows

Disassemble the blocks as follows

第3页

拿出第1条灯光导线

Take out the first light conductor

第4页

把积木拆起如下

Remove the blocks as follows

第5页

将第1节灯光组安装如下

将剩下的灯光导线延箭头方向穿过

Install Section 1 light group as follows

Run the remaining light wires through the arrow

第6页

将第2节灯光组安装如下

将第3节灯光组先放置在楼顶处如图

Install Section 2 light group as follows

Place the third lighting group on the roof first as

shown in the figure

第7页

积木安装还原

拿出第2条灯光导线

Building block installation and restoration

Take out the second light conductor

第8页

将门口的积木拆起如图

拿出2节灯光组安装在第2层底部

Remove the block from the door as shown

Take out 2 lighting sets and install them at the bottom

of the 2nd floor

第9页

将第3条灯光导线和USB穿过积木放置在2层上如图

将第2条灯光导线的最后一个灯光组穿过积木

Place the third light wire and USB through the building blocks on the second layer as shown in the figure

Put the last light set of the second light wire through the block

第10页

拿出积木,将灯光组安装如下

Take out the building blocks and install the lighting

set as follows

第11页

积木安装还原

Building block installation and restoration

第12页

拿出第3条灯光导线

将第1节灯光组安装如下

Take out the thiright conductor

Install Section 1 light group as follows

第13页

把积木拆开

Take apart the blocks

第14页

将第2节灯光组安装如下

Install Section 2 light group as follows

第15页

最后1节灯光组穿过积木并把积木安装还原

如图,将积木拆起

The last light group passes through the building blocks and

restores the building blocks

As shown, remove the blocks

第16页

把灯光导线穿过积木

积木还原

Run light wires through the blocks

Building block reduction

第17页

将1灯灯光组安装如下

积木安装还原

Install the 1 light group as follows

Building block installation and restoration

第18页

把积木安装还原

将第1条灯光导线的最后一个灯光组安装如下

Set the blocks back up

Install the last light group of the first light conductor

as follows

第19页

将灯光接口和电池盒放置在第2层位置上

Place the light interface and battery box in position